Nova Blog

Progress Update #8

11/16/2015 | Posted by jake |

Only around 100 more taps and we’ll have the entires south side of the property finished! Lots going on behind the scenes too, our submersible transfer pump is on the way and we’ve been working on several other things that will eventually need done before the sap starts running.

Lateral lines – 5773/7000 trees
1″ Mainline –  27/36 sections
Wet/Dry lines – 1.5/3 sections

Evaporator Has Arrived!

11/06/2015 | Posted by jake |

We took delivery on our evaporator last night. 6×18′ oil fired Turbo 3 with a 6×10′ Piggyback steam pan. More photos later once it’s fully setup!

IMG_4658

IMG_4652

IMG_4649