Progress Update #10
12/15/2015 | Posted by jake |
The light at the end of the tubing is starting to finally shine, only ~3000′ or so more of mainline left to run lateral lines off of! In other news we’re looking to expand our reverse osmosis (RO) system from a two pump/two membrane 1200 gallon per hour (GPH) to a three/four pump/membrane setup capable of processing 1800-2400 GPH. This will help us process the additional sap from all of the extra maple trees we’ve found. We’ve also located a 42 acre potential sugar bush to add to the company in 2016. Stay tuned, the next update could have all of the lines completed!
Lateral lines – 6674/8000 trees
1″ Mainline – 33/38 sections
Wet/Dry lines – 2.5/3 sections